National Grid Terminals
National Grid has employed ACS to carry out a number of excavations on their main gas terminals at St. Fergus in Aberdeenshire and Bacton in East Anglia and a large compressor site in Aberdeen. There have been 8 excavations with in a 9 month period which ranged from 2.5 to 3.5m deep, with the largest being 6.5m long by 4m wide by 3.5m deep.
|
|
|
St Bedes High School
Enabling works and construction of a new Plant Room
|
|
|
Gas Transmission Compound
Undertaking civils works at three compressor stations (Audley, Warburton and Barton Stacey), where ACS are constructing concrete bases, installing new duct routes, underground chambers & providing new footpaths and protective barrier systems to facilitate the project objective of new analysers & associated telemetry equipment.
|
|
|
HMP Lindholme
Construction of 3 number pump stations and storage tanks up to 9 mtrs deep
|
|